Project Model · Demo G+1 Villa

This Is Your Project… Moment by Moment

A live demo board of a villa project as you would see it: progress, certified spend, stages, and site updates — no promises, just numbers.

0%Progress by month 9
0Certified certificates
0Budget overruns
0Months project duration
Travel Through Time

Drag One Slider… and Watch Your Project Being Built

A feature you won’t find on another contractor’s site: drag the timeline from month 1 to 12 — and watch progress, spend, stages and site updates move before you.

Your Project Time Machine
Progress fills month by month
Spend accrues only with approval
The site log updates before you
Documented Transparency

Transparency You See… Not Just Promised

Every month: certified progress valuation, a documented certificate, an archived photo log, and a cost update — equally clear to owner and consultant.

Documented Monthly
Certified certificate with items & values
Dated site photo log
Cost update vs budget

Your Live Project Board — try it yourself now

Drag the time slider below the board… and watch the project build before your eyes.

Demo G+1 Villa · UAEAED 2.4M budget · 12 months · demo model
LIVE
0%Certified progress
Certified spend (AED)
Budget remaining (AED)
Current stage
Certified certificates

Latest site updates

Month 9 · Finishes

* Demo data simulating a real project; your actual board is built from your certified certificates.

The Full Story: where did these numbers come from?

Every number on the board above has a documented origin — here is its full journey from drawing… to screen.

1
QuantoQUANTITY SURVEYING SOFTWARE

Quanto: From Drawing to a Priced Budget

Before the first day of excavation… your whole project is clear numbers, item by item.

1
Import drawingsArchitectural & structural for all levels (GF · F1 · roof).
2
Auto take-off via measurement systemsFootings, tie beams, columns, beams, blockwork… every quantity references a drawing element & level — with checklists so nothing slips.
3
Build each item’s rateQuantity × unit rate from a customizable library (materials + labor + equipment) for your market & suppliers.
4
Output: an approved priced BOQThe items’ sum = the project budget and its baseline — the 2.4M you saw on the board.
How one item’s price is built live example
Item: footing concrete GF ✓ from drawing39.6 m³
Unit rate AED 1,050/m³ — its build-up:
Mat. 650Labor 300100
MaterialsLaborEquipment & other
Item total39.6 × 1,050 = 41,580 AED
+ 42 more items the same way = the project budget2,400,000 AED

This figure is the “baseline” the board starts from — and every item traces back to its drawing element.

2
DirectFundCONSTRUCTION

DirectFund: From Budget to Progress-Linked Spending

The same Quanto budget becomes disciplined payment stages — not a dirham before certified progress.

1
Split the BOQ into payment stagesExcavation 15% · frame 30% · blockwork 18% · finishes 22% · MEP 12% · handover 3% — the same segments as the board’s bar.
2
Owner-funded procurementKey materials are paid to suppliers directly from your account — never through the contractor’s pocket.
3
Monthly valuation = the certificateActual site work is measured against the same BOQ items (quantity × the approved item rate).
4
Your approval… then releaseNot a dirham moves before your signature — payment goes directly to the entitled. ↻ The cycle repeats to handover.
What the monthly certificate looks like Month 9 · sample
Floor tiling done 120 / 185 m²19,200 AED
Internal plaster 100% ✓24,000 AED
Electrical rough-in done 40%12,800 AED
Month-9 certificate total (all items)168,000 AED
Owner approval ✓Consultant review ✓Direct payment to the entitled ✓↻ Repeats monthly

Every certificate item traces to the approved Quanto rate — no surprise pricing during execution.

3
LIVE BOARD · YOUR PROJECT

The Live Board: Every Approval Appears Before You

The moment a certificate is approved… it turns automatically into numbers on your screen.

Certified progressThe progress ring advances
Certificate valueAdded to “certified spend”
Site worksAppear in the log, documented
“One number flows through your whole project: from the drawing… to the dirham… to the screen.”

The Standard Bill of Quantities (Baseline BOQ)

The items Quanto built from the drawings — grouped by the approved measurement categories, whose totals are the very payment stages on the board. Click any category to expand its items.

Earthworks & FoundationsExcavation · PCC · footings · tie beams · waterproofing · backfill15% of budget360,000+
ItemQtyUnitRateTotal (AED)
Site excavation & grading1,8502851,800
Blinding concrete222605,720
RC footing concrete39.61,05041,580
Ground tie beams28.41,15032,660
Foundation rebar9.2ton2,85026,220
+ 7 more items in this category (neck columns, waterproofing, backfill & compaction…)
Superstructure FrameColumns · beams · slabs · rebar30% of budget720,000+
ItemQtyUnitRateTotal (AED)
RC columns GF + F1461,25057,500
RC beams & slabs1681,180198,240
Frame rebar34ton2,85096,900
Roof slab & parapet521,15059,800
+ 6 more items (stairs, formwork, curing…)
Blockwork & PlasteringBlock · mesh · plaster18% of budget432,000+
ItemQtyUnitRateTotal (AED)
200mm block — external walls3129529,640
100mm block — internal partitions3487225,056
Mesh between courses480m125,760
Internal plaster1,2403847,120
External plaster6204628,520
+ 5 more items (lintels, sills, stiffeners…)
Finishing WorksTiling · paint · doors · aluminum22% of budget528,000+
ItemQtyUnitRateTotal (AED)
Porcelain floor tiling18516029,600
Internal & external painting1,8602240,920
Timber doors14no.1,45020,300
Aluminum & glazing (windows/façades)9652049,920
+ 8 more items (gypsum, marble, balustrade…)
MEP WorksElectrical · plumbing · HVAC12% of budget288,000+
ItemQtyUnitRateTotal (AED)
Electrical rough-in & finish1LS118,000118,000
Plumbing & sanitary1LS92,00092,000
AC units5no.9,20046,000
+ 3 more items (external lighting, pumps…)
Handover & CommissioningCleaning · connections · approvals3% of budget72,000+
ItemQtyUnitRateTotal (AED)
Final cleaning & initial handover1LS28,00028,000
Utility connections & approvals1LS44,00044,000
All items shown for this category
Approved BOQ Total (Baseline)Matches the board budget ✓2,400,000 AED

* Key items shown per category; illustrative figures simulating a real project.

How Do We Guarantee No Sub-Item Is Forgotten?Anatomy of the “blockwork” item — it looks like one line… it is seven.
The blockwork system checklist auto-generated
200mm external / 100mm internal block from WLSm² — openings deducted
Mesh between courses (every 3 courses)lm × 12 AED
RC lintel over every door & window from openings schedulelm × 85 AED
Window sillslm × 65 AED
Stiffener posts for long wallsno. — by wall length
Wall ties to RC columnsno. — every 60 cm
Bedding mortarwithin the block rate build-up

Source: the Wall Lengths Schedule (WLS) — every wall with its length, height and block type, plus its assigned openings schedule. That is why no sub-item slips, however small.

Live example: just one wall J-07 · external perimeter
Wall area (4.20 × 3.20)13.44 m²
− window W2 (1.80 × 1.50)−2.70 m²
= net 200mm block × 9510.74 m² = 1,020 AED
+ lintel over W2 (1.80+0.40) × 852.20 lm = 187 AED
+ window sill × 651.80 lm = 117 AED
+ course mesh: 3 rows × 4.20 × 1212.60 lm = 151 AED
One wall = 4 items priced automatically1,475 AED

Now imagine the whole project: dozens of walls and openings — all measured and priced with nothing forgotten.

The Project’s Monthly Cash Flow

Certified spend month by month, cumulative up to the budget — the very numbers you moved in the time machine.

BUDGET 2.4M AED Month 1: 96,000 AED196kMonth 2: 144,000 AED2144kMonth 3: 192,000 AED3192kMonth 4: 216,000 AED4216kMonth 5: 216,000 AED5216kMonth 6: 216,000 AED6216kMonth 7: 168,000 AED7168kMonth 8: 144,000 AED8144kMonth 9: 120,000 AED9120kMonth 10: 264,000 AED10264kMonth 11: 288,000 AED11288kMonth 12: 336,000 AED12336k Cumulative to 2.4M ✓
Certified monthly spend Cumulative spend Budget cap

* In no month does the cumulative exceed the budget — because spending follows certified progress only.

Planned vs Actual — No Sugar-Coating

The S-curve project managers watch… now in your hands.

Progress % Project months Planned Actual: ahead of plan ✓ You are here · month 9
Certified actual progress Planned progress

What Do You Receive Every Month?

Four documents that make your project an open book.

Certified certificateItems, quantities & values of actual work — before a dirham is paid
Progress reportEach stage’s progress vs the schedule
Dated photo logArchived site photos — see progress with your own eyes
Cost updateSpent & remaining vs budget — no surprises
Owner and consultant see the same data — with the same clarity.

Questions About the Project Board

Is this real project data?+
This is a demo board with illustrative numbers simulating a real villa project. Your actual board is built from your own certified certificates and reports.
How often does the board update?+
A core monthly cycle with each certified valuation, plus site updates and photos throughout the month.
Does the consultant see the same board?+
Yes — owner and consultant see the same numbers with the same clarity, so decisions rest on one shared truth.
Can I see the original documents?+
Every number on the board is backed by a document: a certificate, an approval record, or a dated photo log — documented and retrievable.